Client:
ORCA
Total Drilling Length:
7970m
Location:
Youpwé - Douala, Cameroon
Nos. of Piles:
413
Diameter:
1180/1060mm
Max. Pile Length:
25m

The project consists of the construction of a new building for ORCA. PFS was subcontracted for the execution of deep foundation works. Due to the subsurface conditions, PFS has installed 413 foundation piles, reaching a maximum depth of 25m.