NOVIA Micropiles

Client:
NOVIA Industries
Total Drilling Length:
6570m
Location:
Bonaberi, Douala - Cameroon
Nos. of Piles:
379
Diameter:
180mm
Max. Pile Length:
20.5m

In order to support the existing steel structure and prevent the settlements under the columns due to the loose soil conditions, NOVIA Industries have awarded the remediation works to Progress Foundation Specialists (PFS) for the execution of 379 nos. micropiles. Due to the soil conditions and to limit / prevent the settlement under the existing columns, Progress has executed a total number of 379 micropiles around the columns of the structure.

Related Projects

MIXED USE

For the construction of two (2) new buildings in Bonanjo consisting of 17 and 19 floors, including 2 connected underground parkings, the main contractor “Les

DJEUGA PALACE

Due to design calculation problems and over estimation of the soil capacity under the 13 floors hotel, huge settlement under the raft have affected the